[Federal Register: January 3, 2001 (Volume 66, Number 2)]
[Proposed Rules]               
[Page 473-522]
From the Federal Register Online via GPO Access [wais.access.gpo.gov]
[DOCID:fr03ja01-30]                         
 
[[pp. 473-522]] Effluent Limitations Guidelines, Pretreatment Standards, and New 
Source Performance Standards for the Metal Products and Machinery Point 
Source Category; Proposed Rule

[[Continued from page 472]]

[[Page 473]]

limitation for total sulfide based on potential POTW interference or 
upset associated with discharges of total sulfide from facilities in 
this subcategory. EPA is proposing limitations for TOC and TOP as part 
of a compliance alternative for organic pollutant discharges. (See 
Section XXI.C for a discussion of monitoring flexibility.) The Agency 
based these proposed limitations on the same four EPA sampling episodes 
that EPA discussed in Section XIII.A.3.
4. PSNS Analysis
    Like NSPS, the Agency determined that the cost of compliance with 
PSNS based on Option 4 would make up 4.64 percent of a new facility's 
projected revenues and expects that this would not create a barrier to 
entry. EPA notes that this is a higher percentage than for other 
subcategories and solicits comment on whether EPA should consider 
Option 2 for these facilities.

E. NSPS for the Non-Chromium Anodizing Subcategory

1. Need for NSPS
    EPA expects that new facilities in the Non-Chromium Anodizing 
subcategory will discharge similar quantities of the same pollutants 
that existing sources discharge. EPA notes that it did not identify any 
existing direct dischargers in this subcategory and that estimates of 
costs and pollutant loadings were transferred from the best performing 
indirect dischargers in this subcategory (see Section IX.C). Therefore, 
the need for NSPS regulation is the same as the need for BPT 
regulation. (See Section IX.C.1).
2. Selected NSPS Option
    EPA is proposing New Source Performance Standards for this 
subcategory based on BAT Option 2. As discussed in the BPT analysis for 
this subcategory, non-chromium anodizers discharge large quantities of 
aluminum but have very low levels of other metals in their wastewater. 
EPA determined that Option 2 is capable of removing most of the 
aluminum discharged by facilities in this subcategory and that any 
additional removals achieved by Option 4 are not justified by the 
additional cost.
    The Agency also evaluated not proposing NSPS for facilities in this 
subcategory and instead continuing to require compliance with NSPS 
limitations established under 40 CFR part 433. However, the Agency has 
tentatively rejected this option because these new proposed NSPS 
limitations require an increased removal of TSS and the Agency feels 
that the pollutants proposed for regulation here are more appropriate 
for the non-chromium anodizing industry. The NSPS limitations 
established in 40 CFR part 433 require facilities to meet an average 
monthly discharge of 31 mg/L of TSS and allow for a maximum daily 
discharge of 60 mg/L. These proposed MP&M limitations require non-
chromium anodizers to meet an average monthly discharge for TSS of 22 
mg/L and allow for a monthly maximum discharge of 52 mg/L. EPA believes 
that the costs associated with NSPS are justified by the additional 
removal of TSS from this subcategory. In addition, 40 CFR part 433 
requires non-chromium anodizers to meet effluent limitations for 7 
metal pollutants. EPA's data show that these seven metals are present 
only in very small quantities at non-chromium anodizing facilities. In 
40 CFR part 433, EPA did not establish a limit for aluminum, the metal 
found in the largest quantity in non-chromium anodizers' wastewater. 
The Agency has determined that direct discharging facilities in the 
Non-Chromium Anodizing subcategory should have a limit for aluminum and 
thus is proposing to cover them here. The Agency notes that this will 
reduce the number of pollutants that non-chromium anodizers would have 
to monitor for.
3. Calculation of NSPS Limitations
    The Agency is proposing NSPS limitations for all of the pollutants 
that it proposed BPT and BAT limitations for in this subcategory. The 
NSPS limitations for this subcategory can be found in the proposed rule 
(which accompanies this preamble) at Sec. 438.36. (See Section XXI.C 
for a discussion of monitoring flexibility.)
4. NSPS Analysis
    A barrier to entry analysis is typically performed for new 
facilities by using existing facilities as a model. However, there are 
no existing direct dischargers in this subcategory. Therefore, the 
Agency could not perform an economic analysis in order to determine if 
Option 2 presented a barrier to entry for new facilities in the Non-
Chromium Anodizing subcategory.

F. PSNS for the Non-Chromium Anodizing Subcategory

1. Need for PSNS
    EPA expects that new facilities in the Non-Chromium Anodizing 
subcategory will discharge similar quantities of the same pollutants 
that existing sources discharge and therefore EPA is not proposing 
pretreatment standards for new sources for this subcategory for the 
same reasons it is not proposing PSES for this subcategory. See Section 
XII.F and VI.C.3.

G. NSPS for the Printed Wiring Board Subcategory

1. Need for NSPS
    EPA expects that new facilities in the Printed Wiring Board 
subcategory will discharge similar quantities of the same pollutants 
that existing sources discharge. Therefore, the need for NSPS 
regulation is the same as the need for BPT regulation. (See Section 
IX.D.1).
2. Selected NSPS Option
    EPA is proposing New Source Performance Standards for this 
subcategory based on BAT Option 4. The Agency determined that Option 4 
is the best available demonstrated technology for the removal of 
pollutants in this subcategory. EPA's analytical data shows that Option 
4 is capable of achieving much lower long term averages than Option 2 
for several of the metal pollutants of concern. In addition, EPA's data 
shows that microfiltration greatly reduces the variability in the 
concentration of the metal pollutants in the treatment effluent. 
Although Option 4 costs $162,000 more than Option 2 annually for a new 
facility with a wastewater flow of 25.5 MGY (the wastewater flow for a 
representative direct discharging facility in the Printed Wiring Board 
subcategory), EPA is proposing Option 4 because of the lower levels of 
metal pollutants in the wastewater effluent. EPA is not proposing 
Option 4 for BPT/BAT because of the lack of significant overall 
additional removals and the fact that it removes less COD, O&G, and 
organic pollutants, relative to Option 2. EPA also requests comment on 
basing NSPS on Option 2.
    The Agency also strongly considered proposing NSPS based on 
ultrafiltration for oil and grease removal and chemical precipitation 
followed by sedimentation for TSS and metals removal. This option is 
equivalent to BAT Option 2 with the oil/water separator replaced by an 
ultrafilter. The Agency is soliciting comment and data on this NSPS 
option for the final rule.
3. Calculation of NSPS Limitations
    The Agency is proposing NSPS limitations for all of the pollutants 
that it proposed BPT and BAT limitations for in this subcategory. The 
NSPS limitations for this subcategory can be found in the proposed rule 
(which accompanies this preamble) at Sec. 438.46.

[[Page 474]]

(See Section XXI.C for a discussion of monitoring flexibility.) EPA 
based these proposed regulations on the same four EPA sampling episodes 
that it used to calculate NSPS for the General Metals subcategory. (See 
Section XIII.A.3). As mentioned above, EPA collected analytical 
wastewater treatment data from a printed wiring board manufacturer that 
employed this technology.
4. NSPS Analysis
    The Agency also performed an economic analysis in order to 
determine if Option 4 presented a barrier to entry for new facilities 
in the Printed Wiring Board subcategory. EPA determined that the cost 
of compliance with NSPS based on Option 4 would make up only 0.02 
percent of a new facility's projected revenues. Therefore, EPA 
concluded that NSPS based on Option 4 would not create a barrier to 
entry.

H. PSNS for the Printed Wiring Board Subcategory

1. Need for PSNS
    EPA expects that new facilities in the Printed Wiring Board 
subcategory will discharge similar quantities of the same pollutants 
that existing sources discharge. Therefore, the need for PSNS 
regulation is the same as the need for PSES regulation. (See Section 
XII.G.1).
2. Selected PSNS Option
    EPA is proposing Pretreatment Standards for New Sources for this 
subcategory based on BAT Option 4 for the same reasons it is proposing 
this option for NSPS. It is also requesting comment on PSNS based on 
Option 2. As was the case for PSES, EPA is not proposing a flow cutoff 
exclusion for this subcategory for the same reasons discussed in 
Section XII.G.2, but is requesting comment on a flow cutoff of 1 MGY , 
as with PSES.
    The Agency also strongly considered proposing PSNS based on 
ultrafiltration for oil and grease removal and chemical precipitation 
followed by sedimentation for TSS and metals removal. This option is 
equivalent to BAT Option 2 with the oil/water separator replaced by an 
ultrafilter. The Agency is soliciting comment and data on this PSNS 
option for the final rule.
3. Calculation of PSNS Limitations
    The Agency is proposing PSNS limitations for the same pollutants 
that it proposed PSES regulations. The PSNS limitations for this 
subcategory can be found in the proposed rule (which accompanies this 
preamble) at Sec. 438.47. EPA determined that all of the pollutants 
listed in Sec. 438.47 (except for Total Sulfide, TOC, and TOP) pass 
through POTWs. EPA is proposing a limitation for total sulfide based on 
potential POTW interference or upset associated with discharges of 
total sulfide from facilities in this subcategory. EPA is proposing 
limitations for TOC and TOP as part of a compliance alternative for 
organic pollutant discharges. (See Section XXI.C for a discussion of 
monitoring flexibility.) EPA determined that all of these pollutants 
pass through POTWs. The Agency based these proposed limitations on the 
same four EPA sampling episodes that EPA discussed in Section XIII.A.3. 
As mentioned above, EPA collected analytical wastewater treatment data 
from a printed wiring board manufacturer that employed this technology.
4. PSNS Analysis
    Like NSPS, the Agency determined that the cost of compliance with 
PSNS based on Option 4 would make up only 0.20 percent of a new 
facility's projected revenues and concluded that this would not create 
a barrier to entry.

I. NSPS for the Steel Forming and Finishing Subcategory

1. Need for NSPS
    EPA expects that new facilities in the Steel Forming and Finishing 
subcategory will discharge similar quantities of the same pollutants 
that existing sources discharge. Therefore, the need for NSPS 
regulation is the same as the need for BPT regulation. (See Section 
IX.E.1).
2. Selected NSPS Option
    EPA is proposing New Source Performance Standards for this 
subcategory based on BAT Option 4. The Agency determined that Option 4 
is the best available demonstrated technology for the removal of 
pollutants in this subcategory. EPA's analytical data shows that Option 
4 is capable of achieving much lower long-term averages than Option 2 
for several of the metal pollutants of concern. In addition, EPA's data 
shows that microfiltration greatly reduces the variability in the 
concentration of the metal pollutants in the treatment effluent. 
Although Option 4 costs $42,400 more than Option 2 annually for a new 
facility with a wastewater flow of 18.4 MGY (the wastewater flow for a 
representative direct discharging facilities in the Steel Forming and 
Finishing subcategory), EPA determined that the additional cost of 
Option 4 are justified by the lower levels of metal pollutants in the 
wastewater effluent.
    The Agency also strongly considered proposing NSPS based on 
ultrafiltration for oil and grease removal and chemical precipitation 
followed by a clarifier for TSS and metals removal. This option is 
equivalent to BAT Option 2 with the oil/water separator replaced by an 
ultrafilter. The Agency is soliciting comment and data on this NSPS 
option for the final rule.
3. Calculation of NSPS Limitations
    The Agency is proposing NSPS limitations for all of the pollutants 
that it proposed BPT and BAT limitations for in this subcategory. The 
NSPS limitations for this subcategory can be found in the proposed rule 
(which accompanies this preamble) at Sec. 438.56. (See Section XXI.C 
for a discussion of monitoring flexibility.) The Agency based these 
proposed limitations on the same four EPA sampling episodes that EPA 
discussed in Section XIII.A.3.
4. NSPS Analysis
    The Agency also performed an economic analysis in order to 
determine if Option 4 presented a barrier to entry for new facilities 
in the Steel Forming and Finishing subcategory. EPA determined that the 
cost of compliance with NSPS based on Option 4 would make up only 0.14 
percent of a new facility's projected revenues. Therefore, EPA 
concluded that NSPS based on Option 4 would not create a barrier to 
entry.

J. PSNS for the Steel Forming and Finishing Subcategory

1. Need for PSNS
    EPA expects that new facilities in the Steel Forming and Finishing 
subcategory will discharge similar quantities of the same pollutants 
that existing sources discharge. Therefore, the need for PSNS 
regulation is the same as the need for PSES regulation. (See Section 
XII.H.1).
2. Selected PSNS Option
    EPA is proposing Pretreatment Standards for New Sources for this 
subcategory based on BAT Option 4 for the same reasons it is proposing 
this option for NSPS. In addition, EPA is not proposing a flow cutoff 
exclusion for PSNS for this subcategory for the same reasons that it 
did not propose a flow cutoff for PSES, but is requesting comment on 
flow cutoffs of 1, 2, and 3 MGY as with PSES. (See Section XII.H.)
    The Agency also strongly considered proposing PSNS based on 
ultrafiltration for oil and grease removal and chemical precipitation 
followed by sedimentation for TSS and metals removal. This option is 
equivalent to BAT Option 2 with the

[[Page 475]]

oil/water separator replaced by an ultrafilter. The Agency is 
soliciting comment and data on this PSNS option for the final rule.
3. Calculation of PSNS Limitations
    The Agency is proposing PSNS limitations for the same pollutants 
that it proposed PSES regulations. The PSNS limitations for this 
subcategory can be found in the proposed rule (which accompanies this 
preamble) at Sec. 438.57. EPA determined that all of the pollutants 
listed in Sec. 438.57 (except for Total Sulfide, TOC, and TOP) pass 
through POTWs. EPA is proposing a limitation for total sulfide based on 
potential POTW interference or upset associated with discharges of 
total sulfide from facilities in this subcategory. EPA is proposing 
limitations for TOC and TOP as part of a compliance alternative for 
organic pollutant discharges. (See Section XXI.C for a discussion of 
monitoring flexibility.) The Agency based these proposed limitations on 
the same four EPA sampling episodes that EPA discussed in Section 
XIII.A.3.
4. PSNS Analysis
    Like NSPS, the Agency determined that the cost of compliance with 
PSNS based on Option 4 would make up only 0.17 percent of a new 
facility's projected revenues and concluded that this would not create 
a barrier to entry.

K. NSPS for the Oily Wastes Subcategory

1. Need for NSPS
    EPA expects that new facilities in the Oily Wastes subcategory will 
discharge similar quantities of the same pollutants that existing 
sources discharge. Therefore, the need for NSPS regulation is the same 
as the need for BPT regulation. (See Section IX.F.1).
2. Selected NSPS Option
    EPA is proposing New Source Performance Standards for this 
subcategory based on BAT Option 6, oil-water separation by chemical 
emulsion breaking, gravity separation, and oil skimming. The Agency 
determined that Option 6 is the best available demonstrated technology 
for the removal of pollutants in this subcategory and is proposing this 
option for the same reasons it selected this option for BPT and BAT. 
(See Section IX.F.2).
3. Calculation of NSPS Limitations
    The Agency is proposing NSPS limitations equivalent to those 
proposed for BPT for this subcategory. The NSPS limitations for this 
subcategory can be found in the proposed rule (which accompanies this 
preamble) at Sec. 438.66. (See Section XXI.C for a discussion of 
monitoring flexibility.)
4. NSPS Analysis
    Since EPA is proposing to set NSPS equal to BAT (Option 6) and this 
option is determined to be economically-achievable for these facilities 
under BAT, EPA concluded that NSPS based on Option 6 would not create a 
barrier to entry.

L. PSNS for the Oily Wastes Subcategory

1. Need for PSNS
    EPA expects that new facilities in the Oily Wastes subcategory will 
discharge similar quantities of the same pollutants that existing 
sources discharge. Therefore, the need for PSNS regulation is the same 
as the need for PSES regulation. (See Section XII.I.1).
2. Selected PSNS Option
    EPA is proposing Pretreatment Standards for New Sources for this 
subcategory based on BAT Option 6 for the same reasons it is proposing 
this option for NSPS. In addition, EPA is proposing a 2 MGY flow cutoff 
exclusion for PSNS with serious consideration of a 3 MGY flow cutoff as 
well. This is the same flow cutoff level that EPA is proposing for PSES 
for the existing indirect discharging facilities in the Oily Wastes 
subcategory. The Agency is proposing a 2 MGY flow cutoff for new 
indirect discharging facilities in the Oily Wastes subcategory based on 
the potential POTW permitting burden that would be associated with 
developing and then maintaining permits for new sources with low flows 
and the likelihood that these facilities discharge a small amount of 
pound-equivalents at these low flow rates. The Agency assumes that the 
pound-equivalents per facility for new facilities with flows below or 
equal to 2 MGY would be even lower than the 2 pound-equivalents per 
facility for similarly sized existing sources in this subcategory. The 
Agency concluded that a similar (or even smaller) amount of pollutant 
removal is not justified by the cost of the regulation for new indirect 
Oily Waste facilities discharging less than or equal to 2 MGY.
3. Calculation of PSNS Limitations
    The Agency is proposing PSNS limitations equivalent to PSES for the 
same pollutants that it proposed PSES regulations. The PSNS limitations 
for this subcategory can be found in the proposed rule (which 
accompanies this preamble) at Sec. 438.67. (See Section XII.I.3. for 
PSES discussion and see Section XXI.C for a discussion of monitoring 
flexibility.)
4. PSNS Analysis
    Since EPA is proposing to set PSNS equal to PSES (Option 6) and 
this option is determined to be economically achievable for these 
facilities under PSES, the Agency concluded that this would not create 
a barrier to entry.

M. NSPS for the Railroad Line Maintenance Subcategory

1. Need for NSPS
    EPA expects that new facilities in the Railroad Line Maintenance 
subcategory will discharge similar quantities of the same pollutants 
that existing sources discharge. Therefore, the need for NSPS 
regulation is the same as the need for BPT regulation. (See Section 
IX.G.1.)
2. Selected NSPS Option
    EPA is proposing New Source Performance Standards for this 
subcategory based on BAT Option 10, dissolved air flotation plus in-
process flow control and pollution prevention. The Agency determined 
that Option 10 is the best available demonstrated technology for the 
removal of pollutants in this subcategory and is proposing this option 
for the same reasons it selected this option for BPT and BAT. (See 
Section IX.G.2).
3. Calculation of NSPS Limitations
    The Agency is proposing NSPS limitations equivalent to those 
proposed for BPT for this subcategory. The NSPS limitations for this 
subcategory can be found in the proposed rule (which accompanies this 
preamble) at Sec. 438.76. (See Section XXI.C for a discussion of 
monitoring flexibility.)
4. NSPS Analysis
    EPA notes that railroad line maintenance facilities do not have 
revenue reported at the facility level, and it is therefore not 
possible to compare costs as a percent of facility revenue for new and 
existing facilities in this subcategory. In addition, EPA is proposing 
to set NSPS equal to BAT (Option 10) and has determined this option is 
economically achievable for these facilities under BAT, therefore, EPA 
concluded that NSPS based on Option 10 would not create a barrier to 
entry.

N. PSNS for the Railroad Line Maintenance Subcategory

1. Rationale for Not Proposing PSNS
    EPA expects that new facilities in the Railroad Line Maintenance 
subcategory will discharge similar quantities of the

[[Page 476]]

same pollutants that existing sources discharge. Therefore, EPA is 
proposing to not establish PSNS for this subcategory for the same 
reasons that it did not propose PSES. (See Section XII.J.1).

O. NSPS for the Shipbuilding Dry Dock Subcategory

1. Need for NSPS
    EPA expects that new facilities in the Shipbuilding Dry Dock 
subcategory will discharge similar quantities of the same pollutants 
that existing sources discharge. Therefore, the need for NSPS 
regulation is the same as the need for BPT regulation. (See Section 
IX.H.1).
2. Selected NSPS Option
    EPA is proposing New Source Performance Standards for this 
subcategory based on BAT Option 10, dissolved air flotation plus in-
process flow control and pollution prevention. The Agency determined 
that Option 10 is the best available demonstrated technology for the 
removal of pollutants in this subcategory and is proposing this option 
for the same reasons it selected this option for BPT. (See Section 
IX.H.2).
3. Calculation of NSPS Limitations
    The Agency is proposing NSPS limitations equivalent to those 
proposed for BPT for this subcategory. The NSPS limitations for this 
subcategory can be found in the proposed rule (which accompanies this 
preamble) at Sec. 438.76. (See Section XXI.C for a discussion of 
monitoring flexibility.)
4. NSPS Analysis
    Since EPA is proposing to set NSPS equal to BAT (Option 10) and has 
determined that this option is economically achievable for these 
facilities under BAT, EPA concluded that NSPS based on Option 10 would 
not create a barrier to entry.

P. PSNS for the Shipbuilding Dry Dock Subcategory

1. Rationale for Not Proposing PSNS
    EPA expects that new facilities in the Shipbuilding Dry Dock 
subcategory will discharge similar quantities of the same pollutants 
that existing sources discharge. Therefore, EPA is proposing to not 
establish PSNS for this subcategory for the same reasons that it did 
not propose PSES. (See Section XII.K.1)

XIV. Issues Related to the Methodology Used to Determine POTW 
Performance

    For today's proposal, EPA used its traditional methodology to 
determine POTW performance (percent removal) for toxic and non-
conventional pollutants. POTW performance is a component of the pass-
through methodology used to identify the pollutants to be regulated for 
PSES and PSNS. It is also a component of the analysis to determine net 
pollutant reductions (for both total pounds and toxic pound-
equivalents) for various indirect discharge technology options. 
However, as discussed in more detail below, EPA is evaluating several 
issues related to its traditional methodology for determining POTW 
performance and solicits comments a variety of methodological changes.

A. Assessment of Acceptable POTWs

    EPA developed the principal pass-through analysis for today's MP&M 
proposal by using data from all 50 POTWs that were part of the 50 POTW 
Study data base. Some of these POTWs were not operated to meet the 
secondary treatment requirements at 40 CFR part 133 for all portions of 
their wastestream. Most POTWs today have secondary treatment or better 
in place. EPA estimates that as of 1996, POTWs with at least secondary 
treatment in place service greater than 90 percent of the indirect 
discharging population. If the POTW removal calculations do not reflect 
the upgrades and system improvements that have occurred since the time 
of the 50 POTW Study, they would tend to under-estimate POTW removals. 
This would result in overestimating the pollutant reductions that are 
achieved through the regulation of indirect dischargers, thereby making 
the regulation appear more cost-effective for indirect dischargers than 
it is.
    One partial solution to this methodological issue would be to 
evaluate individual treatment trains in the 50 POTW Study data base, 
and include only those treatment trains that achieved compliance with 
40 CFR part 133 in the analysis of POTW pollutant removal rates. There 
were 29 treatment trains that achieved BOD5 and TSS effluent 
concentrations between 15 mg/l and 45 mg/l during the sampling and 
could potentially be considered reflective of secondary treatment 
(based on 40 CFR 133.102 limitations of 30 mg/l monthly average and 45 
mg/l weekly max for secondary treatment), and an additional 2 treatment 
trains were either trickling filters or waste stabilization ponds that 
achieved BOD5 and TSS effluent concentrations between 40 mg/
l and 65 mg/l and could potentially be considered equivalent to 
secondary treatment pursuant to 40 CFR 133.101(g) (based on 40 CFR 
133.105 limitations of 45 mg/l monthly average and 65 mg/l weekly 
maximum). In addition, 15 treatment trains achieved BOD5 and 
TSS effluent concentrations below 15 mg/l each, and could potentially 
be considered greater than secondary treatment.
    Using data from these 46 treatment trains only would omit the worst 
performers in the 50 POTW Study that are probably not reflective of 
current performance. It might not fully correct, however, for 
additional upgrades and optimization that may have occurred over the 
past two decades.

B. Assessment of Acceptable Data

    EPA developed the pass-through analysis that is the basis for 
today's proposal using POTW data editing criteria that are generally 
consistent with those used for the industry data. Specifically, EPA 
included only data from POTWs for which influent concentrations were 10 
times the analytical minimum (quantitation) level (10xML) if available. 
If none of the average pollutant influent concentrations are at least 
10 times the ML, then EPA retained only data from POTWs for which 
influent concentrations were 2 times the analytical minimum level. 
Because it is difficult to achieve the same pollutant reduction (in 
terms of percent) in a dilute wastestream as in a more concentrated 
wastestream, EPA believes that a 10 X ML editing criteria may 
overestimate the percent removals that are calculated for both industry 
and POTWs in the pass-through analysis.
    As a general rule, more POTW data than industry data is eliminated 
through this editing criteria for the specific pollutants that are 
being examined. This is not surprising since the pass-through analysis 
would not even be performed on pollutants generally found at less than 
10 times the method minimum level in industry since EPA would, in many 
cases, not require pretreatment for such low levels of a pollutant. As 
a result of this imbalance (pollutant influent levels at POTWs being 
less than pollutant influent levels to industrial pretreatment), EPA 
believes that it is possible that this editing criteria may bias the 
pass-through results by over-estimating POTW removals where influent 
concentrations are generally lower. This would result in 
underestimating the pollutant reductions that are achieved through the 
regulation of indirect dischargers thereby making the rule appear less 
cost-effective than it is. On the other hand, there may be little 
difference in percent removals across the range of

[[Page 477]]

influent concentrations generally experienced by POTWs.
    One potential solution to this methodological question would be to 
include data (for both indirect dischargers and POTWs) even if the 
influent concentration is not 10 times the analytical minimum level. 
This solution needs to be considered in context, however, with data 
handling criteria for effluent measurements of ``non-detect'' discussed 
below.

C. Assessment of Removals When Effluent Is Below the Analytical Method 
Minimum Level

    EPA developed the pass-through analysis that is the basis for 
today's proposal using the analytical method minimum level as the 
effluent value when the pollutant was not detected in the effluent. 
This is the approach that is generally used when developing pollutant 
reduction estimates for the regulation, performing cost-effectiveness 
calculations, and developing effluent limitations. EPA believes that 
this methodology may underestimate the performance of the selected 
technology option for both directs and indirects. Once again, this 
would result in underestimating the removals estimated for direct 
dischargers, and thereby making the rule appear less cost-effective 
than it is. For indirect dischargers, EPA believes that the overall 
effect of using the minimum level for non-detect values for both 
industry and POTW data creates a bias for underestimating POTW removals 
in comparison to industry removals. This may result in an 
overestimation of pollutant removals by indirect dischargers, and may 
make the rule appear more cost-effective than it is. [Note that this 
problem is minimized by only using data with influent levels exceeding 
10 X ML, because a non-detect assures that at least 90 percent of the 
pollutant has been removed. It is arguably less important that the true 
removal may be greater than 90 percent, rather than exactly 90 percent. 
Using a less stringent editing criteria of 2 X ML as discussed above 
would exacerbate this problem. If the influent were only 2 X ML, then 
removals greater than 50 percent could never be measured.]
    One potential alternative would be to assume a value of one half of 
the minimum level for effluent values of non-detect. This approach 
would have to be applied uniformly for the indirect dischargers as well 
as the POTWs in order for the percent removal calculations to be 
reasonable.
    For a more detailed discussion of alternative approaches to the 
POTW pass-through analysis, see the Appendix to Section 7 of the 
Technical Development Document. EPA solicits comment on the 
significance of each of these methodological issues and the potential 
alternatives.

XV. Methodology for Estimating Costs and Pollutant Reductions

    EPA estimated industry-wide compliance costs and pollutant loadings 
using model sites based on technical questionnaire respondents and a 
computerized design and cost model for the MP&M technology options (see 
Sections 11 and 12 of the Technical Development Document for a detailed 
discussion of EPA's MP&M Design & Cost Model). The Agency estimated 
industry-wide costs and pollutant loadings for several technology 
options based on technologies designed for each subcategory of model 
sites. EPA used these model sites to estimate costs for 63,000 MP&M 
wastewater-discharging sites nationwide using statistically calculated 
industry weights (i.e., survey sample weights). EPA notes that once the 
low flow exclusion is applied, the number of sites expected to incur 
costs under the MP&M regulation is 10,300.
    There are 890 sites which indicated that they were water 
dischargers on their technical questionnaire and provided EPA with 
enough data to include them in the cost model. EPA assessed each of the 
890 sites selected to determine the unit operations, wastewater 
characteristics and treatment technologies currently in place at the 
sites.
    Based on the information provided by the sites in their 
questionnaire responses, follow-up letters, and phone calls, EPA 
classified each wastewater stream by the type of unit operation (e.g., 
machining, electroplating, acid treatment, etc.) and base metal type 
(e.g., steel, aluminum, zinc, etc.). The Agency used the following 
additional questionnaire data to characterize process wastewater 
streams: wastewater discharge flow rate, production rate, operating 
schedule, and discharge destination. Many of the sites provided these 
data for all wastewater streams generated on site. For sites that did 
not provide complete data, EPA either estimated the missing data based 
on technical considerations specific to the site, or statistically 
imputed the data. The Agency modeled the concentration of each 
pollutant in each wastewater stream from field sampling of wastewater 
discharges from the unit operations at MP&M sites. EPA used 
questionnaire responses to identify the following information about 
end-of-pipe technologies in place at MP&M sites: the types of treatment 
units in place; the unit operations discharging process wastewater to 
each treatment unit; and the operating schedule of each treatment unit.
    EPA developed a computerized design and cost model to estimate 
compliance costs and pollutant loadings for the MP&M technology 
options, taking into account each site's level of treatment in place. 
As a conservative estimate for estimating baseline (prior to compliance 
with these proposed regulations) pollutant loadings, EPA assumed that 
all sites with treatment currently in place (including those sites not 
currently covered by the Metal Finishing regulations) were currently 
meeting the long-term average (LTA) concentrations (i.e., design 
concentrations) for the pollutants limited under the Metal Finishing 
effluent guidelines (40 CFR part 433) with the exception of cyanide and 
were meeting the LTA concentrations achieved by EPA's sampled MP&M BAT 
facilities for cyanide and other pollutants of concern. For sites that 
did not report treatment in place, EPA based baseline pollutant 
loadings on EPA's unit operation-by-unit operation sampling data for 
raw wastewater. The Agency programmed the model with technology-
specific modules which calculated the costs for various combinations of 
technologies included in the technology options for each subcategory. 
EPA based design and cost data on MP&M site data, literature data, and 
vendor data. The Agency developed technology-specific cost modules for 
the in-process pollution prevention and water use reduction 
technologies and end-of-pipe treatment technologies discussed in 
Section VII.A of this notice.
    The model provided the following types of information for each 
technology designed for a model site: capital costs; operating and 
maintenance costs; electricity used and associated cost; sludge 
generation and associated disposal costs; waste oil generation and 
associated disposal costs; water use reduction and associated cost 
credit; chemical usage reduction and associated cost credit; effluent 
flow rate; and effluent pollutant concentrations. This data enabled EPA 
to develop site by site compliance costs and pollutant reductions for 
the costed sites.
    If contract hauling of wastewater for off-site treatment and 
disposal was less costly than on-site treatment, EPA estimated costs 
assuming the model site would contract haul the wastewater. EPA made 
this assessment on a technology-specific basis. When estimating costs 
for sludge disposal, EPA assumed all sludge to be F006

[[Page 478]]

listed (or other F-listed hazardous waste) hazardous waste under RCRA 
(40 CFR 261.31) and would, therefore, be disposed of off-site as 
hazardous waste. As a conservative estimate for the model, EPA did not 
allow the time for storage of the sludge prior to disposal to exceed 90 
days, regardless of the facilities RCRA generator status (i.e., exempt, 
small, large). EPA notes that on March 8, 2000 (65 FR 12377), the 
Agency published a final regulation in the Federal Register extending 
the accumulation time, under RCRA, for certain wastewater treatment 
sludges from electroplating processes to be held on-site without 
requiring a hazardous waste storage permit. Facilities implementing 
pollution prevention, recycling and metals recovery meeting certain 
requirements can accumulate F006 sludge for up to 180 days for large 
quantity generators (or 270 days for small quantity generators).
    After estimation of capital and operating and maintenance costs, 
EPA calculated the total capital investment (TCI), and the total 
annualized cost (TAC). The Agency assumed that facilities meeting local 
limitations or national effluent limitation guidelines and pretreatment 
standards will already incur monitoring costs. EPA solicits comment on 
the whether facilities will incur additional monitoring costs to comply 
with today's proposal (and how much that monitoring would cost). EPA 
has incorporated several options for adding additional flexibility in 
regards to monitoring (See Section XXI.C for a discussion on monitoring 
flexibility). EPA expects that these proposed flexibilities will 
decrease the overall burden and costs of analytical wastewater 
monitoring for facilities within the scope of this rule.

XVI. Economic Impact and Social Cost Analysis

A. Introduction

    EPA's economic analyses are presented in the report titled 
``Economic, Environmental, & Benefit Analysis of the Proposed Metal 
Products & Machinery Rule [EPA-821-B-00-008] (hereafter referred to as 
the ``EEBA''). This report presents the social costs and benefits of 
the proposed rule and alternatives, and estimates the expected economic 
impacts of compliance with the proposed rule in terms of facility 
closures and associated losses in employment. Other measures of 
economic impact include firm-level impacts, local community impacts, 
international trade effects, employment effects, and effects on new 
MP&M facilities. An analysis of impacts on small businesses supports 
EPA's compliance with the Regulatory Flexibility Act (RFA) as amended 
by the Small Business Regulatory Enforcement Fairness Act (SBREFA). 
This section of the preamble summarizes the economic impact and social 
cost findings from the EEBA. The reader is referred to the full report 
for the details of these analyses.
    EPA's determination of economic achievability are based on the 
findings reported in the EEBA and discussed below. The options analyzed 
consist of combinations of comparable technology options for the 
different subcategories. The three options analyzed in the economic 
analyses are defined as follows:

                      Table XVI-1.--Regulatory Options Considered in the Economic Analyses
----------------------------------------------------------------------------------------------------------------
             Subcategory                    Proposed rule            Option 2/6/10              Option 4/8
----------------------------------------------------------------------------------------------------------------
General Metals.......................  Technology option 2; 1   Technology option 2....  Technology option 4.
                                        mgy flow cutoff for
                                        indirect dischargers.
Metal Finishing Job Shop.............  Technology option 2....  Technology option 2....  Technology option 4.
Non-Chromium Anodizing...............  Technology option 2; no  Technology option 2....  Technology option 4.
                                        PSES/PSNS for indirect
                                        dischargers.
Printed Wiring Board.................  Technology option 2....  Technology option 2....  Technology option 4.
Steel Forming & Finishing............  Technology option 2....  Technology option 2....  Technology option 4.
Oily Wastes..........................  Technology option 6; 2   Technology option 6....  Technology option 8.
                                        mgy flow cutoff for
                                        indirect dischargers.
Railroad Line Maintenance............  Technology option 10;    Technology option 10...  Technology option 8.
                                        no PSES/PSNS for
                                        indirect dischargers.
Shipbuilding Dry Dock................  Technology option 10;    Technology option 10...  Technology option 8.
                                        no PSES/PSNS for
                                        indirect dischargers.
----------------------------------------------------------------------------------------------------------------
Technology options 1 through 10 are described in Section VIII.A. of the preamble.

Technology options 1, 3, 5, 7 and 9 (without pollution prevention) were 
not further analyzed, because they remove fewer pollutants and cost 
more than the comparable technology options with pollution prevention.
    The economic impact analyses assess how facilities will be affected 
financially by the proposed rule. Key outputs of the facility impact 
analysis include expected facility closures in the MP&M industries, 
associated losses in employment, and the number of facilities 
experiencing financial stress short of closure (``moderate impacts''). 
The findings from the facility impact analysis also provide the basis 
for the following analyses:
     A firm-level analysis, which assesses the impact on the 
financial performance and condition of firms owning MP&M facilities;
     An employment effects analysis, which assesses the 
increase in employment associated with compliance activities, the loss 
of employment due to facility closures, and the net effect on overall 
employment;
     A community impact analysis, which assesses the job losses 
caused by facility closures and job gains associated with compliance;
     A foreign trade analysis, which assesses the effect of the 
proposed rule on the U.S. balance of trade;
     A new source impact analysis, which assesses the effect of 
effluent guidelines on the costs and financial viability of new 
facilities in the MP&M industries; and
     The Initial Regulatory Flexibility Analysis (IFRA), which 
assesses the economic and financial impacts of the proposed rule on 
small entities.

B. Facility Level Impacts

1. Facility Categories Analyzed
    EPA performed economic impact analyses for three categories of 
facilities, using different methodologies to evaluate each of the 
groups. The three groups are:
     Private MP&M Facilities. This group includes privately-
owned facilities that do not perform railroad line maintenance and are 
not owned by governments. This major category

[[Page 479]]

includes private businesses in a wide range of sectors or industries, 
including. This segment includes facilities that manufacture and 
rebuild railroad equipment. Only facilities that repair railroad track 
and equipment along the railroad line are not included.
     Railroad line maintenance facilities maintain and repair 
railroad track, equipment and vehicles.
     Government-owned facilities include MP&M facilities 
operated by municipalities, State agencies and other public sector 
entities such as State universities. Many of these facilities repair, 
rebuild, and maintain buses, trucks, cars, utility vehicles (e.g., snow 
plows and street cleaners), and light machinery.
    The specific methodology used to assess impacts differs for each of 
the three types of MP&M facilities. In each case, EPA established 
thresholds for measures of financial performance and compared the 
facilities' performance before and after compliance with each 
regulatory option with these thresholds.
2. Data Sources for the Facility Impact Analysis
    The economic analyses rely on data provided by the financial 
portion of the detailed questionnaire distributed to MP&M facilities by 
EPA under the authority of Section 308 of the Clean Water Act 
(``Section 308 Survey''). (See Section V.B for information on the MP&M 
survey questionnaires). The survey was conducted in two phases, 
covering different MP&M industries in each phase. The Phase I survey 
covered seven industry sectors and reported data for fiscal years 1987 
to 1989. The Phase II survey covered an additional ten industry sectors 
(all remaining MP&M sectors except Steel Forming and Finishing, which 
was the subject of a separate survey) and reported data for fiscal 
years 1994 to 1996. The survey financial data were extrapolated to 1999 
dollars using the Producer Price Index. The survey financial data 
included three years of income statements and balance sheets for the 
facility; the composition of revenues by customer type and MP&M 
business sector; estimated value of facility assets and liabilities in 
liquidation; borrowing costs; ownership of the facility; and total 
revenues and employment of the owning entity (if separate from the 
facility). The impacts assessed for these sample facilities were 
extrapolated to the national level using facility sample weights that 
are based on the sample design for the industrial detailed surveys.
    Data for facilities in the railroad line maintenance subcategory 
came from a modified version of the Phase II survey administered to 
railroad operating companies. The questionnaire was modified because 
railroad operating companies generally do not monitor financial 
performance or collect financial data at the facility level for line 
maintenance facilities. The railroad operating companies reported the 
number of MP&M facilities in each operating unit, and provided detailed 
operating company financial data and technical data for each line 
maintenance facility.
    Data for the Steel Forming and Finishing Subcategory came from a 
1997 Section 308 survey of iron and steel facilities. This survey 
requested financial data generally similar to that collected by the 
MP&M surveys, including income statements and balance sheets for Fiscal 
Years 1995-1997 for the facility and the parent firm.
    Government-owned MP&M facilities provided data in response to a 
Phase II Section 308 survey of municipal and other government agency 
facilities. This survey requested information on fiscal year 1996 
sources and amounts of revenue and debt levels for both the government 
entity and the MP&M facilities; and demographic data for the population 
served by the government entity.
    In addition to the survey data, a number of secondary sources 
provided data for the analysis. Secondary source data were used to 
characterize background economic and financial conditions in the 
industries subject to the MP&M effluent guideline. Secondary sources 
used in the analysis include:
     Department of Commerce economic census and survey data, 
including the Censuses of Manufactures, Annual Surveys of Manufactures, 
and international trade data;
     The Benchmark Input-Output Tables of the United States, 
published by the Bureau of Economic Analysis in the Department of 
Commerce;
     Price index series from the Bureau of Labor Statistics, 
Department of Labor;
     U.S. Industry and Trade Outlook, published by McGraw-Hill 
and the U.S. Department of Commerce;
     Industry trade publications; and
     Financial publications, including the Value Line 
Investment Survey and Robert Morris Associates annual data summaries.
3. Methodology and Impact Measures for the Facility Level Analysis
a. Private MP&M Facilities
    EPA performed two categories of financial analysis, one to assess 
the potential for facility closures and the other to assess the 
potential for moderate financial impacts on MP&M facilities. These 
analyses considered facility financial condition in the absence of the 
rule (under baseline conditions) and changes in financial condition 
that would result from the proposed rule.
    EPA used two financial tests to estimate closures among general 
MP&M facilities:
     After-Tax Cash Flow: EPA examined after-tax cash flow 
(ATCF) over a three year period to determine the financial condition of 
general MP&M facilities.
     Net Present Value: EPA also performed a net present value 
(NPV) test, which compared the liquidation value of each facility to 
the present value of expected future earnings. A business may close if 
the value of closing (its liquidation value) exceeds its value as an 
ongoing business (calculated as the present value of expected future 
earnings).
    EPA determined that a facility is subject to severe financial 
stress and is a potential closure if ATCF is negative, since businesses 
generally cannot sustain negative cash flows for long periods of time. 
This test used the average of reported financial data over three fiscal 
years. Baseline cash flow is defined as the sum of reported net income 
and depreciation. The measure is widely used within industry in 
evaluating capital investment decisions because both net income and 
depreciation (which is an accounting offset against income, but not an 
actual cash expenditure) are potentially available to finance future 
investment. However, assuming that total baseline cash flow is 
available over an extended time horizon (for example, 15 years) to 
finance investments related to environmental compliance could overstate 
a site's ability to comply. In particular, the cost of existing capital 
equipment (not associated with regulatory compliance) is not netted out 
of cash flow, as it is of income through the subtraction of 
depreciation. Thus, any costs associated with either replacing existing 
capital equipment, or repaying money that was previously borrowed to 
pay for it, are omitted from the facility analysis. EPA requests 
comment on its use of cash flow as a measure of resources available to 
finance environmental compliance and suggestions for alternative 
methodologies. (See Section XXII of today's notice.)
    Where estimates of liquidation values were available, EPA also 
conducted the NPV test. NPV is the present value of expected future 
earnings less the

[[Page 480]]

liquidation value (including closure and post-closure costs) of the 
facility. If NPV is negative, then a business owner is financially 
better off closing the facility and liquidating its assets, rather than 
keeping the facility open. EPA estimated the present value of the 
facility's expected future earnings by discounting its annual after-tax 
cash flow over a fifteen-year period using a 7 percent discount rate. 
EPA presumed that a facility was a potential closure if the facility 
had an NPV less than zero.
    Where liquidation values were available, facilities that failed 
both tests under baseline conditions are baseline closures. Facilities 
that pass at least one of the two tests in the baseline case but then 
fail both tests post-compliance were considered closures due to the 
rule. Where liquidation values were not provided by the survey, EPA 
applied only the ATCF test to identify baseline and regulatory 
closures.
    In many past rules, EPA has used only the cash flow test to predict 
both baseline and regulatory closures. Using both tests presents a 
higher hurdle and thus makes it less likely that a facility 
experiencing stress will be projected to close. Due to data 
limitations, both tests were used for only 18,913 (approximately a 
third) of the 58,421 private MP&M facilities considered in the 
analysis. For the remaining two-thirds of the facilities, only the 
after-tax cash flow test was used. Table XVI-2 shows the impacts on 
estimated closures of using both tests, rather than the cash flow test 
alone, to predict closures.

  Table XVI-2.--Baseline Closures, Regulatory Closures, and National Estimates of Compliance Costs for Private
      MP&M Facilities by Status under Tests for Closures: 18,913 Facilities for Which Both Tests Were Used
----------------------------------------------------------------------------------------------------------------
                                                                                   Status under proposed option
                                                                    Facilities   -------------------------------
                                                     Baseline     remaining open                      Pre-tax
                  Closure test                       closures         in the        Regulatory      compliance
                                                                     baseline        closures      costs  ($1999
                                                                                                     million)
----------------------------------------------------------------------------------------------------------------
Fail ATCF Only..................................           3,211          15,766             225        $1,782.6
Fail NPV Only...................................           4,243          14,734             244         1,657.2
Double Test: Fail ATCF and NPV Text.............           2,711          16,266             169         1,793.4
----------------------------------------------------------------------------------------------------------------

    If the cash test alone had been used, about 500 additional baseline 
closures and 56 additional regulatory closures would have been 
projected for the proposed rule. Depending on the subcategories in 
which these facilities were located, this could have affected EPA's 
achievability determinations in some cases. EPA requests comment on its 
methodology for estimating facility closures for this rule.
    All sellers in an affected market may benefit from higher prices 
when prices rise in response to compliance costs, whether or not they 
incur compliance costs under the rule. Some facilities that have very 
low compliance costs may even gain more from increased prices than they 
lose due to increased costs associated with the rule. The analysis 
takes into account the effect of price increases that are attributable 
to the regulation. The estimated price increases were generally less 
than 1 percent and in no case exceeded 2 percent.
    EPA also identified private MP&M facilities that are not expected 
to close but that might nonetheless experience moderate financial 
impacts as a result of the rule. The analysis of moderate financial 
impacts examined two financial indicators:
     Pre-Tax Return on Assets (PTRA): The ratio of cash 
operating income to total assets measures the facility's profitability.
     Interest Coverage Ratio (ICR): The ratio of cash operating 
income to interest expenses measures the facility's ability to service 
its debt and borrow for capital investments.
    These two measures are among the criteria that creditors and equity 
investors use to determine whether and under what terms to provide 
financing to a business. The PTRA and ICR also provide insight into the 
ability of a business to generate funds for compliance investments 
internally. A business may have some trouble obtaining financing if its 
profitability is low and its ability to pay its continuing interest 
expenses is uncertain. EPA compared baseline and post-compliance PTRA 
to an 8 percent threshold and ICR to a threshold of 4. A facility is 
considered subject to incremental moderate impacts attributable to the 
proposed regulation if its PTRA and its ICR both pass these thresholds 
in the baseline but it fails one or both of the tests after compliance 
with the rule. Facilities failing one of the tests in the baseline and 
both tests post-compliance were not counted as experiencing moderate 
impacts, but this may in some cases be indicative of moderate rule-
related impacts as well.
    EPA assumed that MP&M facilities would be able to recover some of 
their regulatory costs by raising prices to their customers. An 
analysis of the potential for cost recovery considered conditions in 
each individual MP&M industrial sector industry (e.g. aircraft, 
aerospace, electronic equipment, etc.) Cost pass-through factors were 
estimated for each sector. The cost pass-through factor blends findings 
from two separate analyses to estimate a composite measure of pass-
through potential:
     An econometric analysis of the historical relationship 
between output prices and changes in input costs; and
     An analysis of indicators of pass-through potential based 
on market structure and performance.
    Market structure factors include:
     Market power based on the degree of horizontal and 
vertical integration;
     Extent of competition from foreign suppliers (in both 
domestic and export markets);
     Barriers to competition as indicated by above normal, 
risk-adjusted profitability; and
     Long term growth trends in the industry.
The analysis of pass-through potential indicates the percentage of 
compliance costs that EPA expects firms subject to regulation to 
recover from customers through increased prices. The estimated 
percentage price increases were very small for the proposed rule, 
ranging from 0.02 percent to less than two percent in different 
sectors. This analysis can be found in Appendix B of the EEBA.
    Table XVI-3 summarizes the measures used to assess impacts for 
private MP&M facilities.

[[Page 481]]



                Table XVI-3.--Summary of Facility Impact Methodology for Private MP&M Facilities
----------------------------------------------------------------------------------------------------------------
                                                                                             Significance of
           Impact category                   Description                Criteria             negative finding
----------------------------------------------------------------------------------------------------------------
Baseline Closure.....................  Identifies facilities    1. After-tax cash flow   Facilities failing both
                                        that are in jeopardy     (ATCF) negative? and     tests are considered
                                        of financial failure    2. Liquidation value      baseline closures and
                                        independent of the       exceed going concern     excluded from
                                        proposed regulation.     value (NPV test)?.       subsequent analyses.
Post-Compliance Closure..............  Identifies facilities    1. Post-compliance       Facilities failing both
                                        that are likely to       after-tax cash flow      tests are projected to
                                        close instead of         (ATCF) negative? and     close as the result of
                                        implementing the        2. Liquidation value      regulation--an
                                        pollution prevention     exceed post-compliance   incremental severe
                                        and treatment systems    going concern value?.    economic impact.
                                        required to comply
                                        with the rule.
Moderate Financial Impacts...........  Identifies facilities    1. Decline in pre-tax    Facilities passing both
                                        that may have            return on assets         tests in the baseline
                                        difficult financing      (PTRA) to a level that   but failing one or
                                        compliance investments   jeopardizes access to    both tests post-
                                        or on-going business     financing? or            compliance are
                                        investments as a        2. Decline in interest    considered to
                                        result of the rule.      coverage ratio (ICR)     experience incremental
                                                                 to a level that          moderate economic
                                                                 jeopardizes access to    impacts attributable
                                                                 financing?.              to the regulation.
----------------------------------------------------------------------------------------------------------------

b. Railroad Line Maintenance Facilities
    Railroad operators are unlikely to evaluate the financial 
performance of repair and maintenance facilities as separate profit 
centers, and are therefore not likely to estimate revenues at the 
facility level. EPA conducted an analysis of impacts of these 
facilities at the railroad operating company level, and assessed 
whether the combined impact of compliance costs for the regulated 
facilities owned by each operating company would cause a deterioration 
in the company's financial performance. The analysis predicted that 
railroad line maintenance facilities would close only if the railroad 
operating company as a whole was predicted to close, based on the same 
closure tests described above for other private MP&M facilities. 
Railroad facilities other than the line maintenance facilities perform 
the same type of operations as other MP&M facilities and are included 
in the General Metals and Oily Wastes subcategories, depending on their 
MP&M activities.
c. Government-Owned Facilities
    Governments with facilities affected by the proposed rule may take 
one of three actions in response to the rule:
     Replace one or more MP&M municipal facilities with a non-
municipal provider for services;
     Discontinue these services altogether; or
     Pay for compliance and continue operations.
    EPA assumed that all government-owned facilities would continue 
operating under the proposed rule. The economic impact analysis for 
these facilities evaluates whether a government entity would incur a 
major budgetary burden as a result of complying with the proposed rule. 
Like private firms, governments could in some cases minimize the impact 
of the proposed rule on their budgets by discontinuing operations at 
the regulated facility, rather than paying the costs of compliance. 
Unlike the analysis for private sector MP&M facilities, the analysis of 
government impacts did not consider potential closures and therefore 
may overstate the impacts of the rule on governments that own MP&M 
facilities.
    EPA evaluated impacts for government-owned facilities by performing 
three tests.
     Impacts on site-level cost of service: This test assesses 
whether facility compliance costs would exceed one or more percent of 
the total baseline cost of service at that facility. EPA assumed that 
facilities can absorb compliance costs within their current budget if 
the costs do not exceed one percent of total costs in the baseline.
     Impacts on taxpayers: This test compared compliance costs 
to the income of households that are served by the relevant government, 
and that may support the government through taxes and fees. (If the 
government is a regional transit authority, for example, then the 
households included in this analysis are all households in the region 
that provides funding for the transit authority, as reported in the 
Phase II Section 308 survey.) A government might be expected to 
experience impacts if the ratio of total annualized pollution control 
costs per household to median household income exceeds one percent 
post-compliance. This comparison considered the government entity's 
existing pollution control costs plus the compliance costs incurred by 
all of its MP&M facilities under this rule. EPA uses this test in its 
Economic Guidance for Water Quality Standards as a screening measure to 
determine when communities would incur ``little economic impact'' from 
total pollution control costs. EPA recognizes that most local 
governments receive at most a few percent of the income of their tax or 
fee base (and some receive much less). Thus, one percent of median 
income for pollution control costs alone may be a very significant 
share of the local government's total budget.
     Impact on government debt levels: This test assessed the 
impact of financing the capital costs of compliance on the government's 
overall debt burden. The government might be expected to experience 
impacts if financing all of the compliance capital investments would 
increase its total debt service payments to more than 25 percent of 
baseline revenue. This criterion is used in EPA's MUNIPAY model as a 
level beyond which debt service costs might adversely affect a 
community's credit-worthiness. EPA determined that a government 
facility that failed all three tests is likely to suffer severe adverse 
impacts as a result of the rule. As shown in Table XVI-12 below, no 
governments fail the latter two tests. However, 215 facilities failed 
the site-level cost of service test. The governments operating these 
facilities could experience some level of impacts as a result of the 
rule, if these facilities represent a significant cost to their 
budgets. Government owned facilities perform the same type of 
operations as other MP&M facilities and are included in the General 
Metals and Oily Wastes subcategories, depending on their MP&M 
activities.
4. Baseline Closure Analysis
    The estimated baseline closures for both indirect and direct 
discharge facilities are summarized in Table XVI-4. Of the estimated 
62,752 discharging facilities, 6.1 percent or 3,829 facilities

[[Page 482]]

were assessed as baseline closures. The 3,829 baseline closures include 
3,678 indirect dischargers, or 6.3 percent of indirect dischargers, and 
151 direct dischargers, or 3.1 percent of direct dischargers. The 
facilities estimated to close in the baseline analysis are in jeopardy 
of financial failure independent of the proposed rule. These facilities 
were excluded from the post-compliance analysis of regulatory impacts. 
Data on facility start-ups and closures from the Census Statistics of 
U.S. Businesses indicate that between 6 and 12 percent of facilities in 
the major metal products manufacturing industries close in any given 
year. EPA's estimate may therefore understate actual baseline closures 
somewhat.

                                   Table XVI-4.--Summary of Baseline Closures
----------------------------------------------------------------------------------------------------------------
                                                                     Number of      Percent of
                   Subcategory                     Total number      baseline        baseline      Operating in
                                                  of dischargers     closures        closures        baseline
----------------------------------------------------------------------------------------------------------------
General Metals..................................          29,975           3,199            10.7        * 26,776
Metal Finishing Job Shop........................           1,530             286            18.7           1,244
Non-Chromium Anodizing..........................             190              40            21.1             150
Printed Wiring Board............................             635               3             0.5             632
Steel Forming & Finishing.......................             153               6             3.9             147
Oily Wastes.....................................          29,425             295             1.0          29,130
Railroad Line Maintenance.......................             832               0             0.0             832
Shipbuilding Dry Dock...........................              11               0             0.0              11
                                                 ---------------------------------------------------------------
    All Categories..............................          62,752           3,829             6.1       * 58,922
----------------------------------------------------------------------------------------------------------------
* Excludes 64 facilities that close under baseline conditions but that are expected to continue operating under
  the proposed rule.
Note: may not sum to totals due to independent rounding.

    Of the facilities closing in the baseline, 64 are projected to 
continue operating under the proposed rule because they qualify for the 
low flow cutoff (and therefore incur no compliance costs) but benefit 
from price increases caused by the rule. These 64 facilities are not 
considered in the remainder of the economic impact analysis.
5. Facility Level Costs by Subcategory
    The Technical Development Document presents EPA's engineering 
estimates of costs that will be incurred by facilities to comply with 
the proposed rule and other regulatory options. EPA adjusted the 
engineering costs from 1996 to 1999 dollars using the Engineering News-
Record Construction Cost Index (CCI), and adjusted the costs to reflect 
the effect of taxes using the maximum Federal income tax rate of 34 
percent. The annual equivalent of capital and other one-time costs is 
calculated by annualizing costs at a seven percent discount rate over 
an estimated 15 year equipment life.
    The compliance costs of the rule are the costs paid by those 
facilities that continue to operate in compliance with the rule. 
Aggregate compliance costs presented in this section differ from the 
costs presented in Section IX because they exclude costs for facilities 
that are baseline closures or that close due to regulatory 
requirements. They therefore represent only the compliance outlays of 
facilities that continue to operate. Section H presents EPA's estimates 
of social costs, which include costs for regulatory closures. Table 
XVI-5 shows the total annualized compliance costs by subcategory for 
the 9,577 dischargers (direct and indirect) that are subject to 
requirements, make the necessary investments to meet the requirements, 
and continue operating under the proposed rule. The table also presents 
costs for Option 2/6/10 and Option 4/8, but results are discussed for 
only the proposed option to reduce the length of this document.
    Total annualized costs are the sum of the annual operating and 
maintenance costs and the annualized equivalent of capital and other 
one-time costs. Annualized after-tax compliance costs are estimated to 
be $1,328.9 million ($1.33 billion) \3\ per year under the proposed 
rule, of which 13 percent is paid by direct dischargers and 87 percent 
is paid by indirect dischargers. A total of 49,147 indirect dischargers 
are excluded from regulation by the proposed exclusions and low flow 
cutoffs. Total compliance costs would be 36 percent higher under Option 
2/6/10 ($1,812 million per year paid by 57,641 facilities) and 120 
percent higher under Option 4/8 ($2,918 million per year paid by 55,959 
facilities) than under the proposed rule.
---------------------------------------------------------------------------

    \3\ EPA notes that pre-tax annualized compliance costs are 
estimated to be $1.98 billion (in 1999 dollars).

                    Table XVI-5.--Total Annualized Facility * Compliance Costs by Subcategory, Discharge Status and Regulatory Option
                                                               [After-tax, million $1999]
--------------------------------------------------------------------------------------------------------------------------------------------------------
                                                                   Proposed rule                   Option 2/6/10                    Option 4/8
                       Subcategory                       -----------------------------------------------------------------------------------------------
                                                              Direct         Indirect         Direct         Indirect         Direct         Indirect
--------------------------------------------------------------------------------------------------------------------------------------------------------
General Metals..........................................          $132.3          $969.9          $132.3        $1,295.8          $195.1        $1,885.5
Metal Finishing Job Shop................................             0.8            80.1             0.8            80.1             1.5           112.1
Non-Chromium Anodizing..................................  ..............             0.0  ..............            17.5  ..............            26.0
Printed Wiring Board....................................             1.7            93.4             1.7            93.4             3.0           141.2
Steel Forming & Finishing...............................            20.9            14.0            20.9            14.0            22.7            21.8
Oily Wastes.............................................             9.3             4.3             9.3           143.8            50.0           457.4
Railroad Line Maintenance...............................             0.8             0.0             0.8             0.2             0.9             0.4

[[Page 483]]


Shipbuilding Dry Dock...................................             1.4             0.0             1.4             0.1             0.4             0.1
All Categories: Annual Costs............................           167.2         1,161.7           167.2         1,644.9           273.6         2,644.5
All Categories: Number of Regulated Facilities                     4,633           4,944           4,633          53,008           4,615          51,344
 Continuing to Operate Post-Regulation..................
                                                         -----------------------------------------------------------------------------------------------
Total Costs to Industry by Option, Directs + Indirects..              $1,328.9
                                                                      $1,812.1
                                                                     $2,918.1
--------------------------------------------------------------------------------------------------------------------------------------------------------
* This table includes facility compliance costs only. Section XVI.H. discusses the social costs of the rule. The estimates in this table exclude
  baseline and regulatory closures.
Note: May not sum to totals due to independent rounding.

6. Facility Level Impacts by Subcategory
    The findings from the post-compliance impact analyses are 
summarized below, first for the PSES requirements considered for 
indirect discharging facilities, and then for the BAT/BPT options 
considered for direct discharging facilities. A third section 
summarizes the findings for both discharger classes. Impacts are 
discussed for only the proposed option, to reduce the length of the 
document; however, the tables present the results for Option 2/6/10 and 
Option 4/8. Impacts are not presented for Options 1, 3, 5, 7, and 9 
(without pollution prevention) because these options remove fewer 
pollutants and cost more than the comparable Options 2, 4, 6, 8, and 
10.
a. Indirect Dischargers
    Of the 54,270 indirect discharging facilities subject to regulation 
after baseline closures, EPA estimates that 179 facilities or 0.3 
percent could be expected to close as the result of the proposed rule, 
as shown in Table XVI-6. More than 90 percent of the indirect 
dischargers are excluded from the regulation by the low-flow cutoffs 
for the General Metals and Oily Wastes subcategories, and the 
exclusions for Non-Chromium Anodizers, Railroad Line Maintenance and 
Shipbuilding Dry Docks. The employment losses associated with the 
facility closures are estimated at 5,738 full-time equivalent (FTE) 
positions. The estimated losses in employment are probably substantial 
overestimates because the analysis does not account for the likelihood 
that non-closing facilities will absorb some of the employment lost 
from closing facilities. The proposed rule also creates new employment 
demand to build, install, maintain and operate compliance equipment, 
which offset these job losses. These job gains are discussed in Section 
XVI-H.4.
    Another 575 facilities, or one percent of the indirect dischargers 
operating in the baseline, are expected to experience moderate economic 
impacts under the proposed rule, as shown in Table XVI-7. Both closures 
and moderate impacts increase substantially for Option 2/6/10 and 
Option 4/8, compared to the proposed rule.

              Table XVI-6.--Incremental Severe Impacts (Facility Closures) on Indirect Dischargers
----------------------------------------------------------------------------------------------------------------
                                                               Number of facility closures due to the rule
             Subcategory               Total operating  --------------------------------------------------------
                                         in baseline       Proposed rule      Option 2/6/10        Option 4/8
----------------------------------------------------------------------------------------------------------------
General Metals......................             23,140                 24              1,017              2,140
Metal Finishing Job Shops...........              1,231                128                128                393
Non-Chromium Anodizing..............                150                  0                 91                 91
Printed Wiring Board................                620                  7                  7                 25
Steel Forming & Finishing...........                105                  6                  6                  6
Oily Wastes.........................             28,219                 14                 14                271
Railroad Line Maintenance...........                799                  0                  0                  0
Shipbuilding Dry Dock...............                  6                  0                  0                  0
                                     ---------------------------------------------------------------------------
    All Categories..................             54,270                179              1,262             2,925
----------------------------------------------------------------------------------------------------------------
Note: May not sum to totals due to independent rounding.


                       Table XVI-7.--Incremental Moderate Impacts on Indirect Dischargers
----------------------------------------------------------------------------------------------------------------
                                                          Number of facilities experiencing moderate impacts due
                                       Total operating                         to the rule
             Subcategory                 in baseline    --------------------------------------------------------
                                                           Proposed rule      Option 2/6/10        Option 4/8
----------------------------------------------------------------------------------------------------------------
General Metals......................             23,140                153              1,753              1,737
Metal Finishing Job Shops...........              1,231                117                117                117
Non-Chromium Anodizing..............                150                  0                  0                  0
Printed Wiring Board................                620                301                301                315
Steel Forming & Finishing...........                105                  4                  4                  4
Oily Wastes.........................             28,219                  0                  0                 26
Railroad Line Maintenance...........                799                  0                  0                  0
Shipbuilding Dry Dock...............                  6                  0                  0                  0
                                     ---------------------------------------------------------------------------

[[Page 484]]


    All Categories..................             54,270                575              2,175             2,199
----------------------------------------------------------------------------------------------------------------
Note: May not sum to totals due to independent rounding.

    Another 575 facilities, or one percent of the indirect dischargers 
operating in the baseline, are expected to experience moderate economic 
impacts under the proposed rule, as shown in Table XVI-7. Both closures 
and moderate impacts increase substantially for Option 2/6/10 and 
Option 4/8, compared to the proposed rule.
b. Direct Dischargers
    Of the 4,653 direct discharging facilities subject to regulation 
after baseline closures, EPA estimates that 20 facilities or 0.4 
percent could be expected to close as the result of the proposed rule. 
These 20 are all General Metals facilities, and represent 0.6 percent 
of the 3,636 General Metals Direct Dischargers operating in the 
baseline. The employment losses associated with these facility closures 
are estimated at 178 FTEs. Again, estimated losses in employment 
associated with closures are likely to be overstated, because the 
analysis does not account for the likelihood that non-closing 
facilities will absorb some of the employment from closing facilities. 
In addition, compliance requirements at facilities that continue to 
operate will lead to off-setting increases in employment.
    Another 41 facilities, or 0.9 percent of the 4,653 direct 
dischargers operating in the baseline, would be expected to experience 
moderate financial impacts due to the rule, as shown in Table XVI-9.

               Table XVI-8.--Incremental Severe Impacts (Facility Closures) on Direct Dischargers
----------------------------------------------------------------------------------------------------------------
                                                               Number of facility closures due to the rule
             Subcategory              Total in baseline --------------------------------------------------------
                                          operating        Proposed rule      Option 2/6/10        Option 4/8
----------------------------------------------------------------------------------------------------------------
General Metals......................              3,636                 20                 20                 35
Metal Finishing Job Shops...........                 12                  0                  0                  0
Non-Chromium Anodizing *............  .................  .................  .................  .................
Printed Wiring Board................                 11                  0                  0                  0
Steel Forming & Finishing...........                 43                  0                  0                  2
Oily Wastes.........................                911                  0                  0                  0
Railroad Line Maintenance...........                 34                  0                  0                  0
Shipbuilding Dry Dock...............                  6                  0                  0                  0
                                     ---------------------------------------------------------------------------
    All Categories..................              4,653                 20                 20                37
----------------------------------------------------------------------------------------------------------------
* EPA estimates that there are no facilities in the Non-Chromium Anodizing subcategory that discharge directly
  to surface waters.
Note: May not sum to totals due to independent rounding.


                        Table XVI-9.--Incremental Moderate Impacts on Direct Dischargers
----------------------------------------------------------------------------------------------------------------
                                                         Number of facilities experiencing moderate  impacts due
                                       Total operating                         to the rule
             Subcategory               in the baseline  --------------------------------------------------------
                                                           Proposed rule      Option 2/6/10        Option 4/8
----------------------------------------------------------------------------------------------------------------
General Metals......................              3,636                 34                 34                103
Metal Finishing Job Shops...........                 12                  0                  0                  0
Non-Chromium Anodizing *............  .................  .................  .................  .................
Printed Wiring Board................                 11                  0                  0                  0
Steel Forming & Finishing...........                 43                  7                  7                  7
Oily Wastes.........................                911                  0                  0                  0
Railroad Line Maintenance...........                 34                  0                  0                  0
Shipbuilding Dry Dock...............                  6                  0                  0                  0
                                     ---------------------------------------------------------------------------
    All Categories..................              4,653                 41                 41               110
----------------------------------------------------------------------------------------------------------------
* EPA estimates that there are no facilities in the Non-Chromium Anodizing subcategory that discharge directly
  to surface waters.
Note: May not sum to totals due to independent rounding.

c. Summary of Facility Impacts
    Table XVI-10 summarizes the results of the economic impact analysis 
for all facilities and for all regulatory options analyzed. Closures 
and moderate impacts under the proposed option are substantially lower 
than in Option 2/6/10 and Option 4/8. Of the 616 facilities 
experiencing moderate impacts due to the proposed rule, 137 facilities 
fell below the threshold for pre-tax return on assets only, 38 fell 
below the interest coverage ratio threshold only, and 441 fell below 
both thresholds due to the rule. Job losses due to closures are more 
than off-set by job gains associated with compliance requirements under 
the proposed option. (See Section XVI-H.4 for a discussion of 
employment impacts.)

[[Page 485]]



                    Table XVI-10.--Summary of Incremental Facility Impacts for All Facilities
----------------------------------------------------------------------------------------------------------------
                                                                   Regulatory option
             Subcategory              --------------------------------------------------------------------------
                                            Proposed rule            Option 2/6/10              Option 4/8
----------------------------------------------------------------------------------------------------------------
Number of Facilities Operating in      58,922.................  58,922.................  58,922.
 Baseline.
Number of Closures (severe impacts)..  199....................  1,282..................  2,963.
Percent Closing......................  0.3....................  2.2....................  5.0.
Job losses due to closures (FTE-       5,916 (over 3 years)...  16,834 (over 3 years)..  48,070 (over 3 years).
 years).
Job gains due to compliance            8,487 (over 15 years)..  12,023 (over 15 years).  27,535 (over 15 years).
 requirements (FTE-years).
Number of Additional Facilities with   616....................  2,216..................  2,309.
 Moderate Impacts.
Percent with Moderate Impacts........  1.0....................  3.8....................  3.9.
Annualized Compliance Costs (pre-tax,  $1.98..................  $2.67..................  $4.18.
 billion $1999).
Annualized Compliance Costs (after-    $1.33..................  $1.81..................  $2.92.
 tax, billion $1999).
----------------------------------------------------------------------------------------------------------------

C. Firm Level Impacts

    EPA examined the impacts of the proposed rule on firms that own 
MP&M facilities, as well as on the financial condition of the 
facilities themselves. A firm that owns multiple MP&M facilities could 
experience adverse financial impacts at the firm level if its 
facilities are among those that incur significant impacts at the 
facility level. The firm-level analysis is also used to compare impacts 
on small versus large firms, as required by the Regulatory Flexibility 
Act and the Small Business Regulatory Enforcement Fairness Act. (RFA/
SBREFA issues are discussed in Section XX.C of this preamble.)
    EPA compared compliance costs with revenue at the firm level as a 
measure of the relative burden of compliance costs. EPA applied this 
analysis only to MP&M facilities owned by private entities. (Section 
XVI.D discusses impacts on governments that own MP&M facilities). The 
Phase I, Phase II industrial detailed, and Iron & Steel surveys 
identified the parent firm that owns each facility that responded to 
the survey. In addition, the Phase II industrial detailed survey 
requested that respondents provide information on other MP&M facilities 
owned by the same firm, on a voluntary basis. EPA estimated firm-level 
compliance costs by summing costs for all facilities owned by the same 
firm that responded to the survey plus estimated compliance costs for 
additional facilities for which respondents submitted information.
    The Agency was not able to estimate the national numbers of firms 
that own MP&M facilities precisely, because the sample weights based on 
the survey design represent numbers of facilities rather than firms. 
Most MP&M facilities (43,118 of 54,590, or 80 percent) are single-
facility firms, however. These firms can be analyzed using the survey 
weights. In addition, there are 289 firms that own more than one sample 
facility. These firms are included in the analysis with a sample weight 
of one, since it is not known how many firms these 289 sample firms 
represent. EPA's analysis of firm-level impacts is presented in Chapter 
9 of the EEBA.
    Table XVI-11 shows the results of the firm-level analysis. The 
results represent a total of 43,407 MP&M firms (43,118 + 289), owning 
54,590 facilities (43,118 owned by single-facility firms + 11,473 owned 
by multi-facility firms).

 Table XVI-11.--Firm Level Before-Tax Annual Compliance Costs as a Percent of Annual Revenues for Private Small
                                            Businesses: Proposed Rule
----------------------------------------------------------------------------------------------------------------
                                                  Number and percent with before-tax annual compliance  costs/
                                                                    annual revenues equal to:
                                               -----------------------------------------------------------------
       Number of firms in the analysis*             Less than 1%              1-3%                 Over 3%
                                               -----------------------------------------------------------------
                                                  Number    Percent     Number    Percent     Number    Percent
----------------------------------------------------------------------------------------------------------------
43,407........................................     41,236         95      1,070        2.5      1,101       2.5
----------------------------------------------------------------------------------------------------------------
*Firms whose only MP&M facilities close in the baseline are excluded.

    A small percentage (2.5 percent) of the firms in the analysis incur 
before-tax compliance costs equal to 3 percent or more of annual 
revenues. Ninety-five percent incur compliance costs less than 1 
percent of annual revenues, and the remaining 2.5 percent incur costs 
between 1 and 3 percent of revenues. Of 2,171 firms in the analysis 
that incur costs greater than 1 percent of revenues, 636 are single-
facility small firms that were reported in the facility impact analysis 
to close (161 firms) or experience moderate impacts (475 firms) due to 
the rule.
    This analysis is likely to overstate costs at the firm level for 
two reasons. First, it includes compliance costs for facilities that 
are projected to close due to the rule. The estimated compliance costs 
for these facilities are higher than the true cost to the firm of 
shutting down the facility, as illustrated by the detailed facility 
impact analysis that projects closures. Second, the analysis does not 
take account of actions a multi-facility firm might take to reduce its 
compliance costs under the proposed rule. These include transferring 
functions among facilities to consolidate wet processes and take 
advantage of scale economies in wastewater treatment.

D. Impacts on Governments

    The proposed MP&M rule will affect governments in two ways:
     Government-owned MP&M facilities may be directly affected 
by the MP&M regulation and therefore incur compliance costs; and

[[Page 486]]

     Municipalities that own Publically Owned Treatment Works 
(POTWs) that receive influent from MP&M facilities subject to the 
regulation may incur additional costs to implement the proposed rule. 
These include costs associated with permitting MP&M facilities that 
have not been previously permitted, and with repermitting some MP&M 
facilities with existing control mechanisms (e.g., permits) earlier 
than would otherwise be required. In addition, POTWs may elect to issue 
mass-based control mechanisms to some MP&M facilities that currently 
have concentration-based control mechanisms, at an additional cost.
1. Impacts on Government-Owned Facilities
    EPA administered a survey (the ``Municipal Survey'') to government-
owned facilities to assess the cost of the regulation on these 
facilities and the government entities that own them. (See Section V.B 
for a discussion of EPA's data collection efforts.) The survey 
requested information that provides the basis for EPA's analysis of the 
budgetary impacts of the proposed regulation, including the size and 
income of the populations served by the affected government entities; 
the government's current revenues by source, taxable property, debt, 
pollution control spending and bond rating; and the costs, funding 
sources and other characteristics of the MP&M facilities owned by each 
government entity.
    EPA discusses the methodology for assessing impacts on government-
owned facilities in more detail in Section XVI.B.3.c. In summary, EPA 
used three tests to assess whether MP&M facility compliance costs would 
impose major budgetary impacts on the governments that own the 
facilities: impacts on site-level cost of service, impacts on 
taxpayers, and impacts on government debt. The first test assesses 
impacts at the facility level and the second two tests assess impacts 
at the government level. The Agency judged that a government would 
incur major budgetary impacts due to the rule if it failed all three 
tests.
    The two government-level tests are applied incrementally. 
Governments that fail the test in the baseline are not considered to 
experience budgetary impacts attributable to the rule.
    Table XVI-12 provides national estimates of the number of MP&M 
facilities operated by governments that are potentially subject to the 
proposed rule, by type and size of government.

                               Table XVI-12.--Number of Government-Owned Facilities by Type and Size of Government Entity
--------------------------------------------------------------------------------------------------------------------------------------------------------
                                                                                                                         Regional
   Size of government and status under proposed option         Municipal      State  government        County          governmental          Total
                                                               government                            government         authority
--------------------------------------------------------------------------------------------------------------------------------------------------------
Large Governments (population> 50,000)...................                572                366                686                 36              1,660
Small Governments (population =50,000)...................              2,191  .................                481  .................              2,672
                                                          ----------------------------------------------------------------------------------------------
    All Governments......................................              2,763                366              1,167                 36              4,332
--------------------------------------------------------------------------------------------------------------------------------------------------------

    Table XVI-13 summarizes the status of government-owned facilities 
under the various regulatory options, their compliance costs and 
measures of impacts on government that own MP&M facilities.

    Table XVI-13.--Number of Regulated Government-Owned Facilities, Compliance Costs and Budgetary Impacts by
                                                Regulatory Option
----------------------------------------------------------------------------------------------------------------
                                                           Proposed option    Option 2/6/10        Option 4/8
----------------------------------------------------------------------------------------------------------------
Total Number of Government-Owned Facilities............              4,332              4,332              4,332
Number of facilities exempted by low-flow cutoff.......              3,603  .................  .................
Number of facilities subject to regulation.............                729              4,332              4,332
Compliance costs ($1999 million).......................              $14.1              $64.8             $224.7
Number of facilities with compliance costs > one                       215
 percent of baseline cost of service*..................
Number of governments failing the ``impact on                            0
 taxpayers'' criterion**...............................
Number of governments failing the ``impacts on                           0
 government debt'' criterion***........................
Number of governments failing all three impacts                          0
 criteria +............................................
----------------------------------------------------------------------------------------------------------------
* Annualized compliance costs as a percent of total facility costs and expenditures, including operating,
  overhead and debt service costs and expenses.
** Based on comparison of compliance costs for all facilities owned by the government to the income of
  households that are served by the relevant government. A government is judged to experience impacts if the
  proposed rule results in a ratio of total annualized pollution control costs per household to median household
  income that exceeds one percent post-compliance. Includes existing pollution control costs plus the compliance
  costs due to the MP&M rule.
*** Based on comparison of total debt service costs (including costs to finance MP&M capital costs entirely with
  debt) with baseline government revenue. A government is judged to experience impacts if the rule causes its
  total debt service payments to exceed 25% of baseline revenue.
+ A government is judged to experience major budgetary impacts if it has one or more facilities with costs of
  compliance above 1% of baseline cost of service and fails both the taxpayers impact and government debt impact
  tests.

    Table XVI-13 shows that the proposed rule substantially reduces 
costs and impacts relative to the other options considered for 
government-owned facilities, because 3,603 (83 percent) of the 
facilities are exempted under the low flow cutoffs (110 General Metals 
facilities and 3,492 Oily Wastes facilities.) Compliance costs would be 
more than 4\1/2\ times higher under Option 2/6/10 and 16 times higher 
under Option 4.
    An estimated 215 government-owned facilities (5 percent of the 
total) would incur costs under the proposed rule exceeding one percent 
of their baseline cost of service. Therefore, 95 percent of the 
government-owned facilities either incur no costs or are likely to be 
able to absorb the added costs within their existing budgets. None of 
the

[[Page 487]]

governments incur costs that cause them to exceed the thresholds for 
impacts on taxpayers or for government debt burden. EPA therefore 
concludes that the proposed rule will not impose major budgetary 
burdens on any of the governments that own MP&M facilities.
2. POTW Administrative Costs
    EPA also evaluated the costs incurred by governments to administer 
the rule. The rule is not expected to impose any new administrative 
costs associated with direct dischargers, which are already permitted 
by States. However, control authorities will have to issue control 
mechanisms (e.g., permits) for the first time to some indirect 
discharging facilities and will have to accelerate repermitting for 
some indirect dischargers that currently hold control mechanisms.
    The costs of issuing and enforcing permits and control mechanisms 
associated with the proposed rule are discussed in Section XVI.H.3 of 
this preamble. EPA is able to estimate total costs to POTWs, but is not 
able to estimate the costs to any one POTW, since it is not possible to 
determine what POTWs receive discharges from MP&M facilities except for 
those that responded to the surveys.
    EPA estimates that POTWs as a whole will incur incremental average 
annualized costs over 15 years of between $115,000 and $912,000 under 
the proposed rule. The maximum expenditures by all affected POTWs in 
any one year will be between $186,000 and $1,607,000. These costs 
include issuing new control mechanisms (e.g., permits) to facilities 
that do not currently have permits, issuing mass-based permits to some 
facilities that currently have concentration-based permits, and 
repermitting some facilities sooner than would otherwise be required to 
meet the three-year compliance schedule. On average, a POTW's costs for 
the incremental permitting are only $23 to $184 per permitted MP&M 
indirect discharger under the proposed rule.
    EPA is requiring mass-based permits/control mechanisms only for the 
Steel Forming & Finishing subcategory; permits/control mechanisms for 
other subcategories may be concentration-based. EPA is encouraging 
permit writers and control authorities to issue mass-based permits and 
control mechanisms, however, where appropriate and feasible. The 
analysis of permitting costs assumes for costing purposes that one-
third of the new or reissued permits/control mechanisms in 
subcategories other than Steel Forming & Finishing will be mass-based.
    EPA expects that these increases in costs will be partially offset 
by reductions in government administrative costs for facilities that 
are already permitted under local limits and that will be repermitted 
under this rule. The proposed technical guidance provided by EPA as a 
part of this rulemaking may reduce the research required by permit 
writers/control authorities in developing permits and control 
mechanisms based on Best Professional Judgement (BPJ) for industrial 
dischargers not previously covered by a categorical standard or a water 
quality standard. Further, the establishment of discharge standards may 
reduce the frequency of evidentiary hearings. The promulgation of 
limitations may also enable EPA and the authorized States to cover more 
facilities under general permits. EPA did not estimate these cost 
savings to permitting authorities that may result from the rule.

E. Community Level Impacts

    EPA considered the potential impacts of changes in employment due 
to the proposed rule on the communities where MP&M facilities are 
located. Changes in employment due to the rule include both job losses 
that occur when facilities close and job gains associated with 
facilities' compliance activities. EPA estimated that a total of 5,916 
jobs would be lost at the 199 facilities projected to close under the 
proposed rule. At the same time, EPA estimated that manufacturing and 
installing compliance equipment would lead to 4,488 full-time 
equivalent (FTE) positions, and that operating and maintaining 
compliance systems would result in another 286 FTEs per year. Over a 15 
year analysis period, the net effect of job gains and losses caused by 
the rule is an increase of 2,575 FTE-years or an average of 172 FTEs 
per year. This estimate assumes that workers that lose their job are 
unemployed for an average of one year, and that compliance investments 
and closures occur evenly over the first three years after 
promulgation. This estimate of employment impacts is likely to 
understate the net increase, because it ignores the fact that some 
production and employment lost at closing plants is likely to result in 
increased production and employment at other MP&M facilities. (EPA's 
analysis of employment impacts is discussed in more detail in Section 
XVI-H.4 below and in Chapter 6 of the EEBA.)
    Given the projected overall increase in employment due to the 
proposed rule, EPA does not expect the rule to have significant impacts 
at the community level. It is not possible to predict precisely where 
the job gains and losses will occur. However, facilities that are 
projected to close due to the rule have employment ranging from 2 to 
205 FTEs. MP&M facilities tend to be located in industrialized urban 
areas, and closures of this size are not likely to have a major impact 
on a local economy.

F. Foreign Trade Impacts

    U.S. MP&M producers as a group exported products with a value of 
$380.3 billion in 1999. Imports to the U.S. of the same products in 
1999 totaled $539.1 billion, resulting in an overall net MP&M commodity 
trade deficit of $153.8 billion. Some MP&M sectors contribute to a 
positive commodity trade balance (e.g. aircraft, with a $37.0 billion 
positive balance in 1999). In other sectors, substantially more 
products are imported than exported (e.g. motor vehicles, with a net 
negative balance of $96.8 billion.) Exports and imports by MP&M sector 
are discussed in Chapter 3 of the EEBA.
    The proposed rule will have an impact on the balance of trade in 
MP&M products to the extent that prices for MP&M products increase and 
MP&M facilities reduce production. Imports may increase if domestic 
customers switch from domestic suppliers to foreign suppliers of MP&M 
products, and exports may decrease if foreign customers switch from 
purchasing U.S. exports to other suppliers. On the other hand, business 
lost by the regulated MP&M facilities due to their increased costs may 
be captured by other domestic producers.
    Section XVI.B of this preamble and Chapter 5 of the EEBA describe 
EPA's analysis of changes in output that are expected to result from 
the proposed rule. EPA assessed the impact of these market-level 
changes on the U.S. balance of trade using information provided by the 
industrial general surveys on the source of competition in domestic and 
foreign markets. This analysis allocates the value of changes in output 
for each facility that is projected to close due to the rule to 
exports, imports or domestic sales, based on the predominant source of 
competition in each market reported in the surveys.
    Table XVI-14 shows the results of this analysis. The table compares 
the projected changes in exports, imports and balance of trade 
(expressed in $1999) to baseline 1999 values for both the MP&M 
industries and for the U.S. balance of trade in commodities as a whole. 
The projected changes in trade under the proposed rule have a very

[[Page 488]]

small impact on the balance of trade. The total U.S. balance of trade 
in commodities would decline by less than 0.01 percent and the balance 
of trade in the MP&M industries would decline by 0.01 percent.

                              Table XVI-14.--Proposed Rule Impacts on Foreign Trade
                                                 [Million $1999]
----------------------------------------------------------------------------------------------------------------
                                                                   1999 value of   1999 value of    Balance of
                                                                      exports         imports          Trade
----------------------------------------------------------------------------------------------------------------
                                                    Baseline
----------------------------------------------------------------------------------------------------------------
U.S. Commodity Trade............................................         695,797       1,024,618       (328,821)
MP&M Industries.................................................         380,305         534,141       (153,836)
----------------------------------------------------------------------------------------------------------------
                                                 Post-Compliance
----------------------------------------------------------------------------------------------------------------
Change Due to the Proposed Rule.................................               0            21.1          (21.1)
Percent Change In U.S. Commodity Trade Balance..................              0%           0.01%          0.01%
Percent Change in MP&M Industries Trade Balance.................              0%           0.01%         0.01%
----------------------------------------------------------------------------------------------------------------
Source: U.S. Census and U.S. Environmental Protection Agency.

G. Impacts on New Facilities

    EPA assessed the impacts of the proposed rule on new facilities 
based on the characteristics of a model facility in each subcategory 
and (in some cases) discharge category (direct and indirect). 
Engineering estimates of compliance costs for Option 2/6/10 and Option 
4/8 for a representative facility reflect the typical flow size and 
other technical characteristics of facilities in each category. (See 
the Technical Development Document.) Table XVI-15 lists the compliance 
costs and flow size for a representative model facility in each 
category, along with the regulatory option considered for each 
subcategory.
    In absence of the MP&M rule, new sources in the Metal Finishing Job 
Shop and Printed Wiring Board subcategories would comply with 40 CFR 
part 433 new source requirements, and Steel Forming & Finishing new 
sources would comply with 40 CFR part 420 new source requirements. 
Therefore, the analysis considers only the incremental costs of 
proposed MP&M new source requirements beyond those baseline 
requirements.
    EPA estimated facility revenues for the model facilities based on 
the revenues reported for existing facilities in the Section 308 
surveys. The analysis excludes facilities that are projected to close 
or to experience moderate economic impacts in the baseline, since the 
economic characteristics of these financially-weak facilities are 
unlikely to be representative of new facilities. EPA sorted the 
existing financially-sound facilities in each subcategory/discharge 
status by flow size, and identified facilities in each quartile based 
on flow size. The Agency then identified the flow size quartile that 
the hypothetical facility would fall into. Finally, EPA calculated the 
average revenue for the existing facilities in that same flow size 
quartile, and assumed that the hypothetical new facility would have 
revenues equal to that average. Table XVI-15 shows the facility revenue 
estimated for each model facility.
    EPA calculated compliance costs as a percentage of post-compliance 
revenues as a measure of impacts. The projected revenues include 
estimated prices increases due to the rule. The analysis assumes that 
new sources would benefit from the small price increases resulting from 
the proposed rule for existing sources, and applies the same percentage 
price increase to calculate post-regulation revenues for the new 
sources. Table XVI-15 shows before-tax annual compliance costs as a 
percent of facility post-regulation revenues.
    Finally, Table XVI-15 presents the cost-to-revenue percentage 
estimated for new facilities in each subcategory.

                                                            Table XVI-15.--New Source Impacts
--------------------------------------------------------------------------------------------------------------------------------------------------------
                                                                                  New source         Annualized      Facility Revenue
              Subcategory                Discharge status   Existing source        options        compliance costs     \c\ ($1999)     New Source ACC as
                                                            options proposed    considered \a\      \b\ ($1999)                           % of Revenue
--------------------------------------------------------------------------------------------------------------------------------------------------------
General Metals........................                  I                  2                  4           $393,220       $417,071,318               0.09
General Metals........................                  D                  2                  4            167,342        398,818,659               0.04
Metal Finishing Job Shops.............                  I                  2                  4             65,369          1,428,443               4.64
Metal Finishing Job Shops.............                  D                  2                  4             70,735          5,089,823               1.41
Non-Chromium Anodizing................                  I                  2                  4             97,108         24,201,166               0.40
Oily Wastes...........................                  I                  6                  8            355,874        474,228,616               0.08
Oily Wastes...........................                  D                  6                  8             37,815        116,772,943               0.03
Printed Wiring Board..................                  I                  2                  4             70,563         35,930,097               0.20
Printed Wiring Board..................                  D                  2                  4            160,184      1,029,783,596               0.02
Railroad Line Maintenance.............                I&D                 10                  8            184,261               n.a.               n.a.
Shipbuilding Dry Dock.................                I&D                 10                  8            220,492        192,018,827               0.11
Steel Forming & Finishing.............                  I                  2                  4            114,851         69,640,244               0.17
Steel Forming & Finishing.............                  D                  2                  4             46,945         32,759,295              0.14
--------------------------------------------------------------------------------------------------------------------------------------------------------
Note: Technology Options 1 through 10 are described in Section VIII.A of the preamble.
a EPA is not proposing the new source option considered in this analysis for the Non-Chromium Anodizing, Oily Wastes, Railroad Line Maintenance, and
  Shipbuilding Dry Dock subcategories. See Section XIII for a discussion on new source options selection.
b Incremental to baseline new source requirements (found in 40 CFR 433 and 420, as applicable) for Metal Finishing Job Shop, Printed Wiring Board and
  Steel Forming & Finishing new sources.
c Equal to the average revenues of existing facilities in the same quartile based on flow size of the new source model facility, excluding existing
  facilities that close or experience moderate impacts in the baseline. Assumes the same percentage price increases for new as for existing sources
  under the proposed option.
d Includes existing facilities in all flow categories that continue operating post-compliance.


[[Page 489]]

    New sources in all but the Metal Finishing Job Shop direct 
discharger subcategory incur costs that are below one percent of post-
regulation revenues. Cost increases of this magnitude are unlikely to 
place new facilities at a competitive disadvantage relative to existing 
sources. Moreover, costs as a percentage of revenues are generally 
comparable for new sources and existing sources with which they will 
compete.
    Railroad line maintenance facilities do not have revenue reported 
at the facility level, and it is therefore not possible to compare 
costs as a percent of facility revenue for new and existing facilities 
in this subcategory. The representative new source railroad line 
maintenance facility would incur annualized costs ($184,261) that are 
somewhat higher than those incurred by existing facilities in this 
subcategory (which range from zero to $122,042.)
    See Section XIII for a discussion of new source options selection. 
EPA notes that it did not select the ``New Source Option Considered'' 
in Table XVI-15, above, for the Non-Chromium Anodizing, Oily Wastes, 
Railroad Line Maintenance, and Shipbuilding Dry Dock subcategories, but 
rather selected a lower cost option for new sources.

H. Social Costs

1. Components of Social Costs
    The social costs of regulatory actions are the opportunity costs to 
society of employing scarce resources in pollution control activity. 
The largest component of economic costs to society is the cost incurred 
by MP&M facilities for the labor, equipment, material, and other 
economic resources needed to comply with the proposed rule.
    The social costs associated with the proposed MP&M regulation 
differ from the compliance costs estimated to assess impacts on the 
regulated facilities and firms, because of different treatment of 
taxes. Social costs include compliance costs that are considered on a 
before-tax basis. Privately-owned facilities are able to deduct the 
costs of compliance as business expenses, reduce their tax liability 
for a given level of revenue, and thereby share the burden of the costs 
with other taxpayers. The burden is shared with other taxpayers because 
the Federal government loses the money saved by industry through tax 
shields. The cost to society includes the costs borne by industry, as 
well as the cost borne by the Federal government through lost tax 
revenues. The cost to society, therefore, is higher than the cost to 
industry. The annualized lost Federal tax revenues can be calculated as 
the difference between the annualized cost before and after tax 
shields.
    Social costs also include lost producers' and consumers' surplus 
that result when the quantity of goods and services produced decreases 
as a result of the rule. Lost producers' surplus is measured as the 
difference between revenues earned and the cost of production for the 
lost production. Lost consumers' surplus is the difference between the 
price paid by consumers for the lost production and the maximum amount 
they would have been willing to pay for those goods and services. 
Calculating lost producers' and consumers' surplus accurately requires 
knowledge of the characteristics of market supply and demand for each 
affected industry. EPA instead calculated an upper-bound estimate of 
social compliance costs using the simplifying assumption that all 
facilities continue operating in compliance with the rule, and pay the 
associated compliance costs (i.e., assuming that there are no 
regulation-related closures.) This provides an upper-bound estimate of 
social costs because, for facilities predicted to close, continuing to 
operate and incurring compliance costs is more costly than closing the 
facility with the lost producers' and consumers' surplus associated 
with the closure.
    In addition to the resource costs to society associated with 
compliance, the estimated social cost includes two other cost elements: 
the cost to local governments of implementing the rule and the costs 
associated with unemployment that may result from the proposed 
regulation. The government administration costs include the costs to 
POTWs of permitting and compliance monitoring and enforcement 
activities. The unemployment-related costs include the cost of 
administering unemployment programs for workers who would lose 
employment, and an estimate of the amount that workers would be willing 
to pay to avoid involuntary unemployment.
2. Resource Cost of Compliance
    The resource costs of compliance are the value of society's 
productive resources--including labor, equipment, and materials--
expended to achieve the reductions in effluent discharges required by 
the proposed rule. The social costs of these resources are higher than 
the costs incurred by facilities because facilities are able to deduct 
the costs from their taxable income. The costs to society, however, are 
the full value of the resources used, whether they are paid for by the 
regulated facilities or by all taxpayers in the form of lost tax 
revenues. EPA calculated costs at a 7 percent rate. EPA included 
facilities predicted to close due to the rule when calculating social 
costs.
    The estimated after-tax private compliance costs incurred by 
facilities, excluding costs for facilities that close, are $1.3 
billion. The estimated social value of these compliance costs, 
calculated before-tax assuming no regulatory closures, is $2.0 billion. 
This represents the value to society of the resources that would be 
used to comply with the proposed rule if all facilities continued to 
operate rather than some closing due to the rule. This estimate 
represents an upper-bound social value of the compliance resources 
associated with the proposed rule.
3. Cost of Administering the Proposed Regulation
    EPA estimated the cost to governments of administering the proposed 
regulation, including the use of labor and material resources to write 
permits/control mechanisms under the regulation and to conduct 
compliance monitoring and enforcement activities.
    EPA does not expect increases in administrative costs for 
facilities that discharge their wastewater directly to surface water, 
because the National Pollution Discharge Elimination System (NPDES) 
permit program requires that these facilities hold permits. POTWs will 
incur additional permitting costs for indirect dischargers that do not 
already have a control mechanism (e.g., permit) prior to implementation 
of the proposed rule.
    Information on the baseline number of indirect dischargers with 
control mechanisms comes from the industrial detailed facility surveys, 
which reported the baseline permit status of each MP&M facility. (See 
Section V.B for a description of EPA's survey questionnaires.) EPA 
estimated costs and impacts for these facilities. Results of the impact 
analysis indicate that of the 58,922 MP&M facilities continuing to 
operate in the baseline (including 64 avoided baseline closures), 199 
facilities are expected to close rather than comply with the 
regulation. Another 49,147 are excluded or fall below the proposed low 
flow cut-offs. Of the 9,577 facilities that are expected to continue 
operating and comply with the regulation, 4,633 facilities are direct 
dischargers and 4,944 are indirect dischargers. EPA estimates that 
4,296 of the indirect dischargers already have permits or other control 
mechanisms (629 with concentration-based permits and 3,667 with mass-
based permits) and that 648 indirect discharging facilities will be 
required to get a permit/control mechanism for the first time.

[[Page 490]]

    EPA conducted the POTW survey of 150 POTWs to support analysis of 
the administrative burdens imposed by the proposed rule on POTWs that 
receive discharges from MP&M facilities. The questionnaire requested 
detailed information on the costs of various activities per facility 
permitted, including estimated hours required to develop and issue 
permits/control mechanisms, provide technical guidance, inspect 
facilities, conduct sampling, review compliance reports, take 
enforcement actions, and repermit facilities. The survey requested this 
information for facilities of different sizes (based on flow). In 
addition, the survey requested information on the frequency with which 
specific administrative activities are required for activities that are 
not required for every permitted facility (such as conducting a public 
hearing). EPA used the POTW survey responses to estimate a range of 
permitting labor hour burdens and costs per MP&M facility permitted, 
with separate estimates for concentration- and mass-based permits/
control mechanisms. This analysis is presented in Appendix C of the 
EEBA.
    Estimated annualized POTW administrative costs for each facility 
issued a new concentration-based control mechanism range from $236 to 
$1,890, and from $240 to $1,924 for each facility issued a new mass-
based control mechanism, with the range depending on the complexity of 
the facility being permitted. EPA applied these costs per facility to 
the estimated number of facilities requiring new control mechanisms or 
conversion of a concentration-based to a mass-based control mechanism 
each year, to estimate the total administrative cost to permitting 
authorities. (See Section XXI.B for a discussion on implementation of 
the MP&M limitations and standards.)
    EPA is requiring mass-based permits/control mechanisms only for the 
Steel Forming and Finishing subcategory. For other subcategories, 
permit writers and control authorities can determine what type of 
permit/control mechanism to issue. EPA is encouraging POTWs to 
institute mass-based limits where possible, however. (See Section 
XXII.B.) For purposes of estimating costs, EPA assumed that all Steel 
Forming and Finishing and one-third of the permits/control mechanisms 
issued in other subcategories will be mass-based.
    Table XVI-16 summarizes the estimated range of administrative costs 
that will be incurred by POTWs under the proposed rule. The estimates 
reflect the low and high estimates of permitting cost per facility, and 
take account of the need to repermit indirect dischargers with existing 
control mechanisms (e.g., permits) within the three year compliance 
period rather than on the normal five-year permitting schedule. These 
estimates are described in detail in Chapter 7 of the EEBA.

         Table XVI-16.--POTW Administrative Costs: Proposed Rule
------------------------------------------------------------------------

------------------------------------------------------------------------
Number of facilities permitted:
    Converted from existing concentration-based to                 * 223
     mass-based......................................
    Issued new concentration-based permit............              * 432
    Issued new mass-based permit.....................              * 216
    Repermitted 1-2 years earlier....................              4,073
Number of closing facilities with existing permits                   143
 not requiring repermitting under the proposed rule..
Total POTW Administrative Costs (net present value of      $1.407-$8.311
 incremental costs over 15 years) (million $1999)....
Total POTW Administrative Costs (annualized over 15       $0.115-$0.912
 years @ 7% (million $1999)..........................
------------------------------------------------------------------------
* Assumes that permitting authorities will chose to issue mass-based
  control mechanisms (e.g., permits) to \1/3\ of the facilities
  requiring new permits, and \1/3\ of the facilities with existing
  concentration-based permits, other than Steel Forming & Finishing.
  Mass-based permits are assumed