Did You Know?

Did you know that Contracting Officers can request subcontracting plan goals on a task order?

In accordance to 19.705-1(b) (2), Contracting Officers placing orders may establish small business subcontracting goals for each order. The prime establishing goals shall not be in the form of a new subcontracting plan as a contract may not have more than one plan (19.705-2(e)).

It is a subcontract goal sheet not a subcontracting plan and should be prepared in accordance with the subcontracting goals under regulation FAR 52.219-9(d) (1) - (6). The goal sheet shall be incorporated into the task order as an attachment at the time of award.